Mission Critical
New Castle, IN


- Dirt Excavated: 72,722 LF
- Data Vaults Installed: 174 Vaults
- Concrete Poured: 15,192 CY
- Dirt Backfilled: 70,688 LF
This project involved the installation of key underground infrastructure to power and connect a state-of-the-art data center. Crews performed detailed excavation, concrete placement, and backfilling for medium-voltage and telecom duct banks—forming the essential conduits for electrical distribution and communication systems. Executed with precision and efficiency, the work provided a durable and well-coordinated foundation to support the data center’s demanding operational requirements and long-term reliability.